  • Centurion CP72SR5 - page 1

    Latest Revision: 02.02.2005 Document Ref.: 1010.D.01.00136_8 Product Code: CP72SR5 D3, D5, A5 SLIDING GA TE AUT OMA TION INST ALLA TION MANU AL ...

  • Centurion CP72SR5 - page 2

    ...

  • Centurion CP72SR5 - page 3

    MAJOR COMPONENTS (TYPICAL D5 SHOWN) - COVER - CONTROLLER (CP80 FOR D3/D5; CP81 FOR A5) - MOTOR (12V DC FOR D3/D5; 220V AC FOR A5) - BA T TERY (12V DC, 7A/H-D3/D5 ONL Y) (OR PSU1/2, IF FIT TED) - CHARGER TRANSFORMER/POWER SUPPL Y (CP84E for D3/D5 or CP83E for A5) (NOT FITTED WHEN PSU1/2 IS USED). - GEARBOX CASING - INTERNAL LIMIT SWITCH (DOSS) - MAN ...

  • Centurion CP72SR5 - page 4

    D3 GA TE MASS (kg) RUN (kgF) T ABLE 1 ST ART (kgF) 25 12 300 D5 60 20 500 D5 Light Industrial 16* 16* 500 A5 *LIMITED BY CAP ACITY OF PSU 22 22 500 2 ...

  • Centurion CP72SR5 - page 5

    ANTI-LIFT B RACKETS - Guide rollers must ensure that the gate is held vertically . - Fit suitable anti-lift brackets . The gap should be <5mm to ensure the gate cannot be lifted off the motor pinion. - For improved safety fit additional support post to prevent gate from falling over if guide rollers fail. 3 39 39 42 40 41 ...

  • Centurion CP72SR5 - page 6

    D5 * 6 36 41 48 56 67 81 100 8 10 12 14 16 18 20 22 24 26 28 30 Pull ( kgf ) Duty Cycle ( % ) A5 with F AN 5 15 20 30 25 80 20 0 0 100 40 120 60 Time (hrs) Duty Cycle ( % ) A5 5 15 20 30 25 80 20 100 40 120 60 Time (hrs) Duty Cycle ( % ) DUTY CYCLE CURVES - FOR THE WARRANTY TO BE V ALID , ENSURE THAT THE DUTY CY CLE IS NOT EXCEEDED FOR THE P ARTICU ...

  • Centurion CP72SR5 - page 7

    9 8 10 6 5 7 3 4 5 † For cable types to be used (e.g. SW A, Cabtyre, Intercom cable etc.) consult your municipal authority for details. * n1 = NUMBER OF CORES REQUIRED B Y INTERCOM # n2 = NUMBER OF CORES REQUIRED BY INTERCOM ‡ sufficient for motor only , increase to suit total load if pillar lights are fitted RECOMMENDED INST ALLA TION AND † ...

  • Centurion CP72SR5 - page 8

    6 MECHANICAL MOUNTING DET AILS Option 1 - Bolt down onto concrete plinth - Ensure motor does not protrude into drive-way install baseplate with centre line 250mm off pillar centre. - Position baseplate (43) with centre of single support stud (45) 105mm from edge of gate (46). (This dimension assumes centre line of rack (47) is 20mm from edge of gat ...

  • Centurion CP72SR5 - page 9

    7 2 m 5 0m L C M10 Nut Use two M12 plated nuts as spacers. M10 Washer M10 x 95 expansion stud Existing concrete plinth ...

  • Centurion CP72SR5 - page 10

    - Ensure motor does not protrude into drive-way install baseplate with centre line 250mm off pillar centre. - Fasten concrete anchors (44) to the baseplate (43) using the M10x45 bolts provided. Ensure that the bolts are well tightened. - Position baseplate (43) with centre of single support stud (45) 105mm from edge of gate (46). (This dimension as ...

  • Centurion CP72SR5 - page 11

    PROVISION FOR CABLES - Ensure cables are fitted through base plate before concreting in place. - Remove knock -outs from gearbox to allow for cable entry . - Route cables in front of battery (D3/D5 motors) as shown above. - Seal cable entry holes with silicone sealer . 9 47 46 43 47 350 mm 30 mm 46 43 ...

  • Centurion CP72SR5 - page 12

    GEARBOX MOUNTING DOWN DET AILS - Leave at least 7mm clearance between the lower gearbox nuts and the baseplate to allow for later adjustment. - Gearbox MUST be firmly located between top & bottom nuts and washers as shown at . Use spring washer to lock top nut in place. - Slide gearbox forwards or backwards to give ±8mm clearance between front ...

  • Centurion CP72SR5 - page 13

    MOUNTING RACK - Attach steel rack to gate using 25x25x2mm angle brackets . Distance between centerline of rack and edge of gate should be 20mm (see ). - For best results support rack every 300mm. - Rack must be mounted level with a 2 - 3mm clearance . 56 55 57 11 55 56 57 ±300 mm l Raise gearbox by an additional 3mm. l Put gearbox into manual mode ...

  • Centurion CP72SR5 - page 14

    MOUNTING RACK CONTINUED 200 - 300mm LEVEL 200mm 58 60 59 12 - A simple way of ensuring correct pitch spacing when joining steel rack is to clamp a small offcut between the two pieces. - Check that weld does not foul with meshing surfaces. - If RAZ ™ rack is used, then start installing from the right hand side of the gate working towards the LHS. ...

  • Centurion CP72SR5 - page 15

    INST ALLING CHAIN DRIVE SYSTEMS - Weld rear anchor plate onto gate such t hat centre line of tensioner pin is in line with top of the shaft on the idler pulley . Allow at least 100mm between idler pulleys and anchor brackets. - Align fixed anchor bracket as for . - Ensure chain direction over sprocket is as shown (see ). IDLER PULLEYS 13 >100mm ...

  • Centurion CP72SR5 - page 16

    SET TING MECHANICAL CL UTCH (A5 ONL Y) - Isolate MAINS POWER. - Remove fan from motor to expose the motor shaft (where applicable). Ensure fan has stopped turning. - Lock shaft using 13mm spanner and use 6mm allen key to adjust sensitivity - Clockwise to increase force . - Recommended maximum push force should not exceed 15kgF . 13mm 6mm 14 <15k ...

  • Centurion CP72SR5 - page 17

    15 - With the gate in the CLOSED position, mount the origin marker (66) a minimum 500mm from the origin sensor (68). (See isometric view (A) or plan view (B) above).Please note this distance will affect the pedestrian opening distance. For minimum pedestrian opening, mount the origin marker at 500mm. The maximum distance of the origin marker is lim ...

  • Centurion CP72SR5 - page 18

    POWER WIRING (SEE P AGE 15 FOR SIGNAL WIRING) 16 - 220V AC MOTOR WITH ST ARTING CAP ACITOR - 220V AC, 1Ø, MAINS SUPPL Y FOR CP84E / CP83E USING REMOV ABLE CONNECTORS - CP83E POWER SUPPL Y TRANSFORMER (A5 MODEL ONL Y) - 220V AC PILLAR LIGHT (NOT AV AILABLE ON CP84XTE PSU) - 12V DC MOTOR - 12V DC LEAD ACID BA T TERY (Amp/HOUR RA TING TO SUIT) - CP84 ...

  • Centurion CP72SR5 - page 19

    SIGNAL WIRING (CP80 AND CP81) COM COM NEG NEG NEG 22 23 24 25 26 27 28 29 N/C N/O 12V 12V 12V 17 - RADIO RECEIVER (OR OTHER TRIGGER e.g. INTERCOM) - INFRA RED BEAM TRANSMIT TER - INFRA RED BEAM RECEIVER (N/C CONT ACT) - FREE EXIT TRIGGER (N/O CONT ACT) † - REMOTE ST ATUS LED (MAX 3 IN P ARALLEL) - PEDESTRIAN TRIGGER (N/O CONT ACT) - HOLIDA Y LOCK ...

  • Centurion CP72SR5 - page 20

    RECOMMENDED LIGHTNING PROTECTION 18 - For optimum lightning protection ensure earth cable from c harger/PSU unit is adequately earthed. - Use ring lug to bond to baseplate mounting stud. - For additional protection bond baseplate to earth spike . - In event of damage to charger/PSU unit disconnect quick release link and push-on connector on control ...

  • Centurion CP72SR5 - page 21

    COMMISSIONING BLOCK DIAGRAM 19 - Check correct motor direction (pg. 20) - Select programme mode (pg. 21) - Setting of gate limits (pg. 22-27) NOTE: D3/D5 LIMITS ARE SET AUTOMA TICALL Y . A5 LIMITS ARE SET MANUALL Y - Function Selections(optional) (pg. 27-28) - Timer/counter settings (optional) (pg. 29-30) Steps 1 to 3 must be done on initial commis ...

  • Centurion CP72SR5 - page 22

    SET TING MOTOR DIRECTION 20 ENSURE THA T MOTOR WIRE COLOURS ARE AS PER T ABLE ABOVE CP80 GA TE CLOSES: - a a b b c TOWARDS LEFT (ABOVE) BLACK BLACK BLUE BL UE BLUE BL UE RED RED BLACK BLACK TOWARDS RIGHT CP81 a TO 220V AC MOTOR TO 12V DC MOTOR b a c CP80 CP81 12V DC 220V AC MOTOR M1 M2 M3 b ...

  • Centurion CP72SR5 - page 23

    SELECTING PROGRAMME MODE 21 STEP 1 - Remove power from control card: - for A5 remove electronics power only - for D3/D5 remove battery power as well as electronics power . STEP 2 - Fit “SET” link . STEP 3 - Reapply power (reversal of STEP 1). ST ATUS LED will flash 5 times on power up. Check that LED L2 and “SET” are ON. LED L2 indicates co ...

  • Centurion CP72SR5 - page 24

    SET TING GA TE LIMITS 22 - Rotate manual release thumbwheel fully clockwise, or until clutch is fully dis-engaged and gate can be moved by hand. D3/D5 ONL Y - Slide gate approximately half way open. See above (FIG. 1). - Re-engage gearbox. A5 ONL Y - Slide gate to fully closed position (FIG. 2). - Leave gearbox dis-engaged. - Skip to page 25-27 and ...

  • Centurion CP72SR5 - page 25

    SET TING GA TE LIMITS (continued) 23 D3/D5 ONL Y (P AGE 23, 24, 25) - Press the TEST pushbutton while monitoring LED L1. - When L1 flashes once, release TEST pushbutton. L2 will go out, L1 will continue to flash once per second. Controller is now in MENU 1 which sets gate limits. NB. Understand the procedure detailed on page 24 before continuing. T ...

  • Centurion CP72SR5 - page 26

    24 1 2 3 4 5 6 1- Gate starts at “crawl” speed to open gate. NB. If gate closes, remove power and reverse motor wires (see page 20) 2- Gate hits “open” end stop and reverses direction running at crawl speed. 3 - Gate hits “closed” end stop and reverses direction running at “FULL ” speed until the marker , then at CRAWL speed to end. ...

  • Centurion CP72SR5 - page 27

    25 TURBO MODE: If desired the set up time can be shortened by manually overriding the automatic “crawl”speed in steps 1, 2, 3 shown on page 24. This is done by pressing and holding the TEST button. The speed increases to FULL speed while the button is depressed. NB. Do not run the gate into the end stops at full speed. CP80 control card L1 L2 S ...

  • Centurion CP72SR5 - page 28

    26 - Start with gate fully closed. - Push gate open (origin marker must have moved well past origin switch). - Push gate closed again. STEP 2 - ENSURE PCB IS IN PROGRAMME MODE (refer procedure page 21) STEP 4 - Push gate to fully “OPEN” position and do not allow gate to reverse. - Press TEST pushbutton until ST ATUS LED comes ON and release. ST ...

  • Centurion CP72SR5 - page 29

    27 CP81 control card L1 L2 STA TUS TEST SET CP81 control card L1 74 L2 STA TUS TEST SET EXIT GA TE LIMITS ROUTINE (A5 ONL Y) If the gate limits described on page 26 are successfully completed, then LED L2 will be ON. - Position SET link as shown above to exit programming unless proceeding to other menus. 74 FUNCTIONS SELECT Several different functi ...

  • Centurion CP72SR5 - page 30

    28 T ABLE 2 AUTO CL OSE POSITIVE CL OSE MODE MODE PREFLASHING* F ACTORY DEF AUL TS HIGHLIGHTED COLLISION SENSITIVITY ON ON 2 1 1 1 1 1 3 3 3 2 2 2 2 2 4 4 4 7 10 9 MAIN MENU SUB DIVISION OF MAIN MENU OFF OFF CONDOMINIUM MODE 2 MEDIUM PIRAC MODE 3 REVERSING HIGH LO W ST ANDARD MODE1 OFF No of times L1 flashes No of times ST ATUS must flash ...

  • Centurion CP72SR5 - page 31

    29 TIMER and COUNTER SET TING V arious timers and counters can be programmed. The procedure is described below in conjunction with T able 3, page 30. STEP 1 - Ensure controller is in Programme Mode (see page 21). STEP 2 - Press and hold the TEST pushbutton while monitoring LED L1. STEP 3 - L1 will flash once then go off, twice in short succession t ...

  • Centurion CP72SR5 - page 32

    30 T ABLE 3 PEDESTRIAN AUTOCL OSE NORMAL AUTOCL OSE AUTOCL OSE OVERRIDE PREFLASH TIME COURTESY LIGHT COLLISION COUNTER 11 1 SEC 1 SEC 1 SEC 1 SEC 10 SEC 1 COUNT 3 6 12 5 8 MAIN MENU No of times L1 flashes Each flash of ST ATUS represents UNIT OF MEASURE CRAWL DIST ANCE (D3/D5) 350 MM † 13 COAST MODE (A5) 10 MM 13 15 SEC 5 SEC 5 SEC 4 COUNTS 5 SEC ...

  • Centurion CP72SR5 - page 33

    31 PROCEDURE TO PROGRAMME CONTROLLER BACK TO F ACTORY SET TINGS 1. REMOVE POWER (POWER SUPPL Y AND BA T TERY IF D3 or D5 ). 2. FIT THE " SET " LINK. 3. CONNECT " PED " AND " FRX " TO "COM". 4. RECONNECT POWER. L1 AND L2 WILL ILLUMINA TE. 5. REMOVE THE POWER (BA T TERY AND POWER SUPPL Y). 6. REMOVE THE " ...

  • Centurion CP72SR5 - page 34

    32 2. GA TE DOES NOT RUN BUT THE RELA YS ENERGISE WHEN THE UNIT IS ACTIVA TED. 2.1 Faulty motor circuit 2.1.1 Faulty motor relay / FET 2.1.2 Motor fuse blown (replace with 16/20A slow blow 5x20mm) 2.1.3 Fuseholder making bad contact. 2.1.4 Worn motor brushes 2.1.5 Loose motor wire 2.1.6 Faulty controller 3. GA TE OPENS ON ITS OWN. 3.1 Permanent tri ...

  • Centurion CP72SR5 - page 35

    ...

  • Centurion CP72SR5 - page 36

    CENTURION THE AUTOMA TIC CHOICE CENTURION SYSTEMS (PTY) L TD HEAD OFFICE: TEL: +27 (0)11 699-2400, F AX: +27 (0)11 704-3412 or 462-6669 148 EPSOM AVENUE, NORTH RIDING P .O . BOX 506, CRAMERVIEW , 2060 SOUTH AFRICA WEB: http://www .centsys.co.za General information e-mail: info@centsys.co.za FOR TECHNICAL SUPPORT CONT ACT : E C H O - L I N E , N A M ...

Fabbricante Centurion Categoria Oxygen Equipment

I documenti che otteniamo dal fabbricante del dispositivoCenturion CP72SR5 possono essere suddivisi in diversi gruppi. Questi sono tra gli altri:
- disegni tecnici Centurion
- manuali per l’uso CP72SR5
- schede prodotto Centurion
- opuscoli
- o etichette energetiche Centurion CP72SR5
Tutti sono importanti, ma le informazioni più importanti dal punto di vista di utilizzo del dispositivo possono essere trovate nel manuale per l’uso Centurion CP72SR5.

Un gruppo di documenti denominato manuali per l’uso, è anche suddiviso in tipi più specifici, come: Manuali di installazione Centurion CP72SR5, manuali di manutenzione, brevi manuali o manuali utente Centurion CP72SR5. A seconda delle esigenze, si dovrebbe cercare il documento necessario. Nel nostro sito web, puoi visualizzare il manuale più popolare per l'uso del prodotto Centurion CP72SR5.

Manuali per l’uso simili

Manuale completo del dispositivo Centurion CP72SR5, come deve essere?
Il manuale per l’uso, denominato anche istruzioni per l’uso, o semplicemente il manuale è un documento tecnico progettato per aiutare ad utilizzare Centurion CP72SR5 dagli utenti. I manuali sono di solito scritti da uno scrittore tecnico, ma in un linguaggio accessibile a tutti gli utenti Centurion CP72SR5.

Il manuale per l’uso completo Centurion, dovrebbe includere vari elementi di base. Alcuni di loro sono meno importanti, come ad esempio: copertina / pagina del titolo o pagina di autore. Tuttavia, la parte rimanente, dovrebbe fornire informazioni importanti dal punto di vista dell'utente.

1. Introduzione e la guida su come utilizzare il manuale Centurion CP72SR5 - All'inizio di ogni manuale, dovremmo trovare indizi su come utilizzare il documento. Dovrebbe contenere informazioni sulla posizione dell’indice Centurion CP72SR5, FAQ o i problemi più comuni : i punti che sono più spesso cercati dagli utenti di ogni manuale
2. Indice - elenco di tutti i suggerimenti per Centurion CP72SR5 che possono essere trovati nel documento corrente
3. Suggerimenti su come utilizzare le funzioni di base del dispositivo Centurion CP72SR5 - che ci dovrebbe aiutare nei primi passi durante l'uso Centurion CP72SR5
4. Troubleshooting - sequenza sistematica delle attività che vi aiuterà a diagnosticare e, successivamente, risolvere i problemi più importanti del Centurion CP72SR5
5. FAQ - domande più frequenti
6. Dettagli di contatto Informazioni su dove cercare il contatto con il fabbricante / servizio Centurion CP72SR5 in un dato paese, se il problema non può essere risolto da noi stessi.

Hai una domanda su Centurion CP72SR5?

Utilizza il modulo sottostante

Se non hai risolto il problema con Centurion CP72SR5 con l'aiuto del manuale che hai trovato, fai una domanda utilizzando il modulo sottostante. Se un utente ha avuto un problema simile con Centurion CP72SR5 è probabile che voglia condividere il modo di risolverlo.

Riscrivi il testo dall’immagine

Commenti (0)